Brownfield project / filler replacement survey

Replacement Filling Machine for an Existing Line

A replacement filler must match measured physical and utility handovers, not just the old machine nameplate. Record the current centerline, directions, elevations, water, electrical, controls, access and cutover constraints before selecting a reference platform.

Replacement Filling Machine for an Existing Line - Bottle labeling conveying coding and end-of-line packaging equipment path
Allot Tech 2026 catalog imageReference values require project-specific confirmation.
Answer first

Survey the existing filler boundary in operating and stopped conditions, identify which connected equipment will remain, and record every dimension and signal with a source. The replacement scope ends at the agreed filler handovers; whole-line rebalance and ramp-up belong to production-system planning.

Brownfield survey / measured handovers

Survey the installed condition before selecting the replacement

Photographs support the survey but do not replace measured dimensions, signal records or access checks.

Survey areaEvidence to captureReplacement decision
Physical positionCenterline, footprint, height, level and line directionMachine envelope and base work
Bottle handoversInfeed/outfeed elevation, guides and transfer geometryReuse, adapter or replacement scope
Product waterConnection point, pipe route and operating boundaryPiping and control modification
Electrical and controlsSupply, panel, cable route, signals and safety boundaryReuse or redesign at filler level
Access and removalDoors, roof, lifting route, floor load and working clearanceDelivery and removal method
CutoverShutdown window, temporary work and site responsibilityInstallation and commissioning sequence

Reference values require project-specific confirmation. This worksheet stops at the filling-machine handovers; whole-line balancing remains outside this domain.

01

Suitable for

Projects that match this page decision

  • Plants replacing one PET still-water filling machine
  • Capacity or reliability upgrades that retain connected equipment
  • Projects able to schedule a measured site survey
02

Not suitable for

Boundaries that need a different platform or review

  • A complete new-line redesign presented as a filler replacement
  • Selecting from old nameplate BPH without bottle and interface evidence
  • Assuming existing drawings match the installed condition
03

Inputs required

Evidence to provide before confirmation

  • Measured machine position, centerline, direction and elevations
  • Existing bottle formats, necks, caps and actual change parts
  • Water, electrical, drainage and control handovers
  • Access, lifting, shutdown, removal and cutover constraints
04

Machine function

What happens at this machine or decision boundary

  • Compare the proposed filler envelope with the measured opening.
  • Identify reusable, modified and replaced handovers.
  • Create a cutover scope with explicit buyer and supplier responsibilities.
05

Configuration decisions

Options that must appear in the proposal

  • Keep, modify or replace each connected interface
  • Temporary production or shutdown plan during replacement
  • Required site work before delivery and commissioning
06

Interface requirements

Upstream, downstream and utility handovers

  • Empty-bottle infeed elevation, direction and transfer condition
  • Product-water and electrical connection points
  • Filled-bottle outfeed, downstream clearance and machine-level signals
07

Buyer risks

Questions to close before order

  • Designing from outdated layout drawings
  • Hidden floor, access or lifting restrictions
  • Unpriced adapter, conveyor, piping or control modifications
08

FAT checks

How to verify the agreed basis

  • Reproduce approved bottle formats and declared machine-level handovers.
  • Record any temporary simulation used instead of existing equipment.
  • Carry site-only checks into a separate commissioning action list.
09

Quotation scope

What the commercial offer should state

  • Survey assumptions and measured interface schedule
  • Removal, adaptation and new-machine scope boundaries
  • Site work, installation, commissioning and cutover responsibility
  • Open dimensions, signals and conditions requiring confirmation

Search questions / buyer answers

Questions buyers ask before requesting a quotation

What information is required before confirming Replacement Filling Machine for an Existing Line?

Measured machine position, centerline, direction and elevations. Existing bottle formats, necks, caps and actual change parts. Water, electrical, drainage and control handovers. Access, lifting, shutdown, removal and cutover constraints.

What should the quotation state for Replacement Filling Machine for an Existing Line?

Survey assumptions and measured interface schedule. Removal, adaptation and new-machine scope boundaries. Site work, installation, commissioning and cutover responsibility. Open dimensions, signals and conditions requiring confirmation.

How should Replacement Filling Machine for an Existing Line be checked during FAT?

Reproduce approved bottle formats and declared machine-level handovers. Record any temporary simulation used instead of existing equipment. Carry site-only checks into a separate commissioning action list.

Allot Tech / replacement-filling-machine-existing-line

Turn this decision into a comparable machine scope

Send the bottle, cap, reference output, existing equipment and destination. Final values are confirmed in the project proposal.