Bottled-Water Filling Machine FAT Acceptance Checklist

A FAT should test the contracted machine with approved bottles and caps under a written method. A short demonstration without recorded inputs and results is not a comparable acceptance test.

Answer first

Agree the reference bottle, cap, continuous run time, output calculation, reject treatment, fill-level method, cap checks, alarm tests and document list before the FAT date. Use the builder below to create a project draft.

Tool 04 / FAT draft

Build a preliminary acceptance checklist

Select the items required for your project, add the sample basis, then download a plain-text draft for supplier review.

Acceptance items
01

Suitable for

Projects that match this page decision

  • Machine-only and machine-plus-interface projects
  • Buyers preparing a remote or in-person FAT
  • Teams aligning purchase, engineering and operations
02

Not suitable for

Boundaries that need a different platform or review

  • Using an unapproved bottle or cap on test day
  • Counting downtime without a predefined rule
  • Signing only from a supplier video with no result sheet
03

Inputs required

Evidence to provide before confirmation

  • Approved bottle and cap revision
  • Contracted reference output and test duration
  • Acceptance method for level, leakage and cap result
  • Required documents, parts and interface simulations
04

Machine function

What happens at this machine or decision boundary

  • The checklist links every acceptance item to evidence.
  • The run record separates planned stops, external starvation and machine faults.
  • Open points remain assigned before shipment release.
05

Configuration decisions

Options that must appear in the proposal

  • Witnessed, remote or recorded FAT
  • Sampling frequency and acceptance limits
  • Which formats and changeover are tested
  • How unresolved items affect shipment
06

Interface requirements

Upstream, downstream and utility handovers

  • Simulated infeed and outfeed conditions
  • Product-water supply used for the test
  • Electrical voltage and control-interface basis
07

Buyer risks

Questions to close before order

  • No agreed output calculation
  • Samples that differ from production supply
  • Missing manuals, drawings, spares or nameplate data
08

FAT checks

How to verify the agreed basis

  • Approved samples, continuous run and actual output
  • Bottle transfer, fill-level consistency, leakage and capping result
  • Alarm/stop logic, change parts, spares, electrical documents and nameplate
09

Quotation scope

What the commercial offer should state

  • FAT location, duration and witness responsibility
  • Included samples, utilities and operators
  • Acceptance record and open-point process
  • Re-test, packing and shipment release responsibility

Allot Tech / fat-acceptance-checklist

Turn this decision into a comparable machine scope

Send the bottle, cap, reference output, existing equipment and destination. Final values are confirmed in the project proposal.